• Line heaters
  • Compressor stations
  • Refrigeration plants
  • Emissions handling systems
  • Dehydration
  • Gas field gathering system design (hydraulics)
  • Single/Dual and Multi-well pad facilities
  • Critically Sour gas facilities
  • High pressure piping design
  • High CO2

EXPERIENCE

Well Tie-Ins and Flexpipe Pipeline Installation

  • Tied in nine (9) new or standing Penn West wells into Keyera gathering system in Strachan, Alhambra, and Medicine River fields.
  • A total of 9,870 meters of 3” OD flexpipe and 2,425 meters of 4” OD flexpipe to bring production from each well to the designated tie-in points.
  • Tie-ins were to Keyera specifications.
  • Wellsites were outfitted with separator tank combo packages and a 45 degree flexpipe riser with full barrel type pig receiver.
  • Process modeling of separators to determine suitability of a smaller separator for the low pressure application. 

Gas Dehydration Facility Project

  • Designed and constructed a gas dehydration plant to accommodate an expected rate of 25 mmscfd of produced sour gas with a field increase of up to 70 mmscfd.
  • Completed flare stack sizing and H2S release rate calculations.
  • Design consisted of three (3) knock out tanks and one (1) flare stack for instantaneous flow of 150 mmscfd.
  • Preparation and submission on Kermit of OGC regulatory requirements including BC-20 and as-builts